What is meant by ‘server nodes in a multi-node servers are NOT designed to be hot-swappable’ (Article 2.1.7 of the Regulation)?

It means that a given server node needs to be powered down first before swapping (without having to power down other server nodes in the system).

Disclaimer: Please note that the European Commission cannot provide a legally binding interpretation of the EU legislation, as this is the sole competence of the European Court of Justice. Any remarks from the European Commission services are without prejudice to the position the Commission might take should related cases arise in a procedure before the Court of Justice.